Why it takes three to seven months

That is a long time to hear about when you have just lost someone, so it is worth knowing where the time goes.

It comes down to a single question: whether we already have your granite. About half the time we do. When we do not, the quarrying and the shipping take five to six months on their own.

Granite in stock
about half our jobs
2 to 3 months
Granite ordered
the other half
6 to 7 months
01234567 months

Bronze markers work the same way. We design the plaque with you and place the order, and bronze usually takes about three months to arrive.

1

What is allowed

Your cemetery decides the size and type of stone, so we start by asking where they are buried.

2

The design

We draw the stone and change it until your family agrees on it.

3

Waiting for the stone

We keep the most common sizes and colors in stock, though the yard is small. If yours is there, this step disappears. If it has to be quarried and shipped, it is five to six months on its own, and it is nearly all of the wait.

4

Cutting and setting

The lettering is cut, and we install the finished stone at the cemetery.

Widths show roughly how the time divides when the granite has to be ordered.

While the stone is in transit, the design is finished and the cemetery pours the foundation it will sit on. We handle that paperwork with them, so there is nothing here for you to chase.

What can push it past seven months

Shipping and weather

Stone travels a long way, and storms and port delays are outside anyone's hands. This is the most common reason a job runs late.

A fully custom design

Original carving and unusual shapes sit outside the normal range. They are a small share of what we make, and we will say so at the start.

Time your family needs

Some families settle on a design in a week. Others take months, especially when several people are weighing in. Both are normal, and we would rather it was right than fast.